Metsa Board is one of the leading European producers of premium fresh fibre paperboards

To meet the growing demand for sustainably produced packaging materials, Metsa Board announced last year an investment to increase the annual folding boxboard production capacity at its Husum mill by 200,000 tonnes.

 

To extend the current folding boxboard capacity, detailed engineering and civil works have been in progress for several months. The board machine will be extended by 54 metres which will require an extension of the machine hall basement.

 

Hakan Jonsson, Project Director at Husum said, “We have built a building in the building to be able to do the extensive civil demolition works safely and at the same time to be able to continue production on BM1.”

 

The extension of the folding boxboard machine has been planned using simulation and 3D models. The dry end area of the board machine will be renewed, and the reel handling will be fully automated. There are also several improvements to the infrastructure to enable a smooth-running operation at the site. All the main machinery purchases for the project have been undertaken, with Valmet as our main machinery supplier.

 

“The team spirit is very good – we are a dedicated team with a positive attitude. The cooperation with machine suppliers and main consultants has worked smoothly,” added Jonsson.

 

The Metsä Board project organisation is now manned with 24 people and on top of that, we have some individuals working part time on the project. More resources for installation management and commissioning activities will be added later. There are presently approximately 30 contractors working on site, mainly in civil works.

 

Speaking on the possibilities of the modern technology, Jonsson said, “The upcoming fully automatic reel handling is impressive and will enable smooth production flows. We’ve conducted a simulation to make sure that there are no bottlenecks built into the system. The operators will be able to focus on the machine performance and the quality of the paperboard.”

 

The start up of the renewed board machine is planned for the autumn of 2023 with full production capacity estimated to be reached by the end of 2025.